2025 ANNUAL REPORT
PALISADE PARK NORTH METROPOLITAN DISTRICT NO. 3

As required by Section 32-1-207(3)(c), C.R.S. and Section XI of the Service Plan for Palisade Park North Metropolitan District No. 3 (the “District”), approved by the City and County of Broomfield, Colorado (the “City”) on August 22, 2017, the following report of activities from January 1, 2025 to December 31, 2025 is hereby submitted.

A.                Boundary changes made: The District did not make any boundary changes during the reporting year.

B.                 Intergovernmental Agreements entered into or terminated: The District did not enter into or terminate any Intergovernmental Agreements during the reporting year.

C.                 Access information to obtain a copy of rules and regulations adopted: The District does not currently have any rules and regulations and there were none proposed during the reporting year.  In the event the District adopts rules and regulations in the future, such documents may be accessed at the offices of McGeady Becher Cortese Williams P.C., 450 E. 17th Avenue, Suite 400, Denver, Colorado 80203, or on the District’s website: https://palisadeparknorthmetropolitandistrict3.specialdistrict.org/.

D.                Summary of litigation involving the District’s public improvements: To our knowledge, the District is not involved in any litigation.

E.                 Status of the District’s construction of public improvements: The District constructed, or financed the construction of, the following public improvements during the reporting year:

·         Filing No. 4 Replat D and Filing No. 5 Replat A Water, Sewer, Storm, Roadway, and Landscaping improvements were completed in 2025.

F.                  Conveyances or dedications of facilities or improvements, constructed by the District, to the City: The following conveyances or dedications of facilities or improvements, constructed or financed by the District, to the City during the reporting year:

·         Water, Sewer, Storm, and Roadway Improvements were dedicated to the City and County of Broomfield.

G.                Final assessed valuation of the District for the reporting year: The final gross total taxable assessed valuation of the District for the reporting year is $15,281,760 and the final net total taxable assessed valuation of the District for the reporting year is $156,827.

H.                Current year’s budget: A copy of the District’s 2026 budget is linked below. 

2026 Budget - Palisade Park North 3.pdf

I.                    Audited financial statements for the reporting year (or application for exemption from audit): A copy of the 2025 Audit is linked below. 

Final 2025 Audit - PPNMD 3

J.                   Notice of any uncured events of default by the District, which continue beyond a ninety (90) day period, under any debt instrument: To our knowledge, there are no uncured events of default by the District which continue beyond a ninety (90) day period.

K.                Any inability of the District to pay its obligations as they come due, in accordance with the terms of such obligations, which continues beyond a ninety (90) day period: To our knowledge, the District has been able to pay its obligations as they come due.

*For accessibility purposes, this is an alternate conforming version of the Annual Report

Audits/Audit Exemption 
Budgets and Mill Levy 
2026 Budget - Palisade Park North 3.pdf

2026 Mill Levy - 69.888 Mills

2025 Budget

2025 Mill Levy - 62.250 Mills

2024 Budget Amendment2024 Budget

2024 Mill Levy - 62.250 Mills

Transparency Notice 

The Transparency Notices for the Districts can be accessed on the Special District Association website:

https://www.sdaco.org/lc/sda-transparency/notice/id/2397

District Map 
Map of the District located in the City and County of Broomfield, Colorado